Bridge Condition Investigation (BCI) through District Bridge Records (DBR) Preparation at Dolakha District
Objectives: After earthquake bridges condition investigation.
Key Activities:
-
Agreement of program.
-
Bridges condition investigation ASE and SM selection.
-
Field visit of bridge sites.
-
Data collection of bridges.
-
Online software bridges data entry.
-
Submission of program report.
Project Period: 3 month (June 16-July 16, 2015 and January 01-February 29, 2016)
Project Location: Dolakha District.
Funding Partner (s): Office of District Development Committee (DDC), Dolakha
Major Achievements:
-
125 bridges condition investigation.
-
29 bridges identification for emergency rehabilitation.
-
52 bridges identification for major maintenance.
-
40 bridges identification for no action required.
-
3 bridge identification for protection.